Category Archives: SAP PS MCQs

How many levels of WBS elements can be created in Project Systems module? | SAP PS mcqs

a. 999 b. 256 c. 99 d. 255 Answer: D

Posted in SAP PS MCQs | Leave a comment

Could a user with Access Control List (ACL) authorization ‘Read’ lock a project? | SAP PS mcqs

a. Yes b. No Answer: A

Posted in SAP PS MCQs | Leave a comment

With reference to material requirements in Project System (PS-MAT), which of the following statements are true? | SAP PS mcqs

a. 9999 components may be created per network. b. Project System supports consignment stock. c. Component scrap is considered during BOM explosion. Answer: A

Posted in SAP PS MCQs | Leave a comment

Which of the following are possible user exits that can be used while processing materials from the Project Systems? | SAP PS mcqs

a. CNEX0009 — EXIT_SAPLCOMK_001 b. CNEX0011 — EXIT_SAPLCOMK_002 c. CNEX0015 — EXIT_SAPLCN10_002 d. CN015AFZ — EXIT_SAPLCNFZ_003 Answer: a, b, c

Posted in SAP PS MCQs | Leave a comment

Which Organization element are mandatory for Creation of the Project Definition in SAP PS ECC? | SAP PS mcqs

a. Controlling Area b. Controlling Area and Company Code c. Controlling Area and Plant d. Controlling Area, Company Code and Proj Currency Answer: a

Posted in SAP PS MCQs | Leave a comment

What are the pre-requisites for distributing work to HR Resources? | SAP PS mcqs

a. In Customizing for the Project System, you must have defined profiles for workforce planning in Resources. b. Assigned work centers to the internally processed activities. c. Assigned one or more labor capacity to a work center. Answer: a, b

Posted in SAP PS MCQs | Leave a comment

Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned? | SAP PS mcqs

a. Persons b. Organizational units c. Jobs d. Positions Answer: a, b, d

Posted in SAP PS MCQs | Leave a comment

Project System has its own Organizational structure, which can be a matrix structure. | SAP PS mcqs

a. True b. False Answer: B

Posted in SAP PS MCQs | Leave a comment

All the currency-dependent data in the Project System is managed in three different currencies in parallel. These are; | SAP PS mcqs

a. Business Area Currency b. Controlling area currency c. Object Currency d. Transaction currency Answer: b, c, d

Posted in SAP PS MCQs | Leave a comment

With reference to Organization Assignments in Project Systems, which of the following statements are true? | SAP PS mcqs

a. Controlling Area & Company Code assignments is mandatory at Project Definition level. b. Currency can be changed Only if the controlling area does not allow different company code currencies. c. Business area assignment is mandatory at Project Definition level. … Continue reading

Posted in SAP PS MCQs | Leave a comment